- Normally situated opposite the excavating area of the mine in order to refill the area (recultivation) where mined product has been removed.
- Last piece of equipment in the Around Pit System - APS continous mining process.
|
|
|
| Main data |
| Materials to be handled | overburden |
| Nominal capacity | 6500 m3/h |
| Receiving boom length | 70 m (230 ft) |
| Discharge boom length | 100 m (328 ft) |
| Belt width | 1800 mm (71 in) |
| Project data |
| Project name | Visonta |
| Location | Hungary |
| Year of delivery | 1986 |
|