- Situated opposite the excavating area of the mine in order to refill the area (recultivation) where mined product has been removed.
- Last piece of equipment in the Around Pit System - APS continous mining process.
|
|
|
| Main data |
| Materials to be handled | overburden |
| Nominal capacity | 2500 m3/h |
| Receiving boom length | 35 m (115 ft) |
| Discharge boom length | 50 m (164 ft) |
| Belt width | 1200 mm (47 in) |
| Project data |
| Project name | Assarel |
| Location | Bulgaria |
| Year of delivery | 1999 |
|