- Mine conveyors together with 4 semi-mobile crushers and 2 spreaders to be used for for the removal of approx. 500 million cubic meters of overburden to open up the coal seams.
- Conveyor system comprises 14 belt conveyors - fixed and shiftable conveyors for the transport of the overburden from the mine to the dumping area.
|
|
|
| Main data |
| Nominal capacity | 2x11000 t/h |
| Material to be handled | overburden |
| Length | 13800 m (45276 ft) |
| Project data |
| Project name | Mae Moh V |
| Location | Thailand |
| Year of delivery | 2002 |
|